SEPTEMBER KEY FIGURES

Sep qtr 12

Jun qtr 12 to Sep qtr 12

Sep qtr 11 to Sep qtr 12

$m

% change

% change


TREND ESTIMATES(a)


Value of work done

Building

19 332.7

-0.9

-3.3

Residential

11 147.5

-0.9

-5.0

Non-residential

8 188.2

-0.8

-0.9

Engineering

32 241.6

4.4

22.4

Total construction

51 681.8

2.6

11.6


SEASONALLY ADJUSTED ESTIMATES(a)


Value of work done

Building

19 257.9

-1.6

-4.9

Residential

11 221.9

0.6

-3.7

Non-residential

8 036.0

-4.5

-6.4

Engineering

32 040.1

3.8

13.9

Total construction

51 298.0

1.7

6.0


(a) Reference year for Chain Volume Measures is 2010-11.

SEPTEMBER KEY POINTS

VALUE OF WORK DONE, CHAIN VOLUME MEASURES

TOTAL CONSTRUCTION

  • The trend estimate for total construction work done rose 2.6% in the September quarter 2012.
  • The seasonally adjusted estimate for total construction work done rose 1.7%, to $51,298.0m in the September quarter.

    BUILDING WORK DONE

  • The trend estimate for total building work done fell 0.9% in the September quarter.
  • The trend estimate for non-residential building work done fell 0.8% in the September quarter.
  • The seasonally adjusted estimate of total building work done fell 1.6%, to $19,257.9m, in the September quarter.

    ENGINEERING WORK DONE

  • The trend estimate for engineering work done rose 4.4% in the September quarter.
  • The seasonally adjusted estimate for engineering work done rose 3.8%, to $32,040.1m, in the September quarter.